Menu
  • © 2024 McCarthy-Bush Corporation
  • Office Hours: Mon–Fri 8am–5pm

12 Commercial Construction Terms to Know Before Signing a Contract

What’s the difference between RFI and RFP? When do OAC meetings start? In the commercial construction industry, it’s easy to get wrapped up in checklists, workflows and schedules. However, we believe specificity and clear communication are keys to providing our clients with a great construction experience. That’s why we’ve compiled a list of the 12 common commercial terms used on a daily basis. We arm our clients with the information they need to make informed decisions that are right for their projects and business.

RFP (Request for Proposal): A document created by a property owner that announces, describes and solicits cost proposals from qualified contractors for a specified project.  It’s common for public entities like schools or other government agencies to issue RFPs.

RFI (Request for Information): A means to clarify ambiguities or fill in gaps in information that appear in the plans or specifications. For example, a concrete subcontractor needs more detail on rebar placement than was shown on the plans, so they submit an RFI to the contractor who either responds to the RFI or forwards it to the architect/engineer for a response.

OAC (Owner, Architect, Contractor) Meetings: Periodic meetings between the owner, architect and contractor to discuss the progress of a project.

Contingency: Money, often a percentage of the total project cost, reserved to cover unexpected project costs that arise during a project. For example, a contractor starts excavating a site and hits bedrock. To remove it, different equipment needs to be brought in and the excavation takes longer than originally estimated. Contingency funds would be used to pay for this unexpected cost.

Allowance: Funds set aside to cover a known cost of an unknown amount. For example, an owner wants to use tile flooring in their front entryway so the contractor budgets for a standard tile material that costs $5 per sq/ft.  The owner ultimately selects an $8 per sq/ft option and agrees to pay the $3 per sq/ft amount by which the actual tile exceeded the allowance.

Change Request: A contractor’s request of the owner to compensate for something that needs to be modified on the project.  For instance, the owner may be considering adding a door to a room. This change is made to the design documents and sent to the contractor for pricing. The contractor issues a Change Request for the additional door.

Change Order: A formal change in a project’s scope, often also impacting construction costs and completion dates. In the Change Request example above, when the owner approves the Change Request for the additional door, a Change Order is issued which formally adds the door to the project for the agreed price and (if applicable) a completion date extension.

Substantial Completion Date: The date an owner can occupy the building for its intended use. For example, if long lead time carpet isn’t yet available to install in a conference room, lack of carpet in that room doesn’t prevent the office building from being used.

Punchlist: A list of scope items that must be completed before a construction project is declared complete. Examples might include: replacing a damaged ceiling tile, touching up paint or ensuring dirt in light fixtures is cleaned.

Final Completion: The date the project is fully and satisfactorily complete, Including the completion of all punchlist items.   The contractor can receive final payment upon final completion.

Consequential Damages: Damages to an owner’s business indirectly resulting from a breach of contract and which are generally foreseeable but not defined at the start of a project. For example, delays in the completion of a project for a manufacturing company that result in the manufacturing company’s inability to complete contracts for its customers.

Liquidated Damages: A sum of money the contractor agrees to pay the owner, typically for each day the contractor completes the project late. For example, a contractor pays the owner of an office building $1,000 per day for every day the office building is completed after the contractual completion date.  The amount cannot be so great that it would be considered a penalty.  Liquidated Damages are typically accompanied by an equal and opposite Early Completion Bonus.

The post 12 Commercial Construction Terms to Know Before Signing a Contract appeared first on Bush Construction.

Next article: »

Have an inquiry?
Contact us.